Process for Industries Unit Set Up in Uttarakhand |
Process for Manufacturing Unit Set Up in Uttarakhand |
Process for Manufacturing Unit Set Up in Uttarakhand | |
1-
Land required |
a-
Lease out land or Transfer Plant in SIIDCUL |
(siidcul
land is govt. land it is lease out only not sell)
SIIDCUL
process transfer of land or plant. |
i- |
Transfer Eligibility Letter | (Time duration 15 days) |
|
|
ii- |
Provisional Transfer
Letter. |(Time duration 15 days) |
|
|
iii- |
Final Transfer
Letter | (Time Duration 15 days) |
|
|
iv- |
Possession Letter
from Siidcul. | (Time Duration 15 days) |
b-
Purchase Land in private industrial
area. |
- (select industrial land and directly registry in the name of company. If land is not industrial then apply form land use change it will take 3 month to 6 month after permission you will pay stamp duty of industrial land and registry land.
2-
Single Windows Project
Approvals | (Time Duration 15 to 30 Days)
a-Generating a Common Application Form (CAF) with
the help of project report
b- Appling for in principle departmental Approvals |
i- |
Pollution Department | (Time
duration 5 Days)
|
ii- |
Fire | (Time duration 5
Days) |
iii- |
Electricity | (Time
duration 5 Days) |
iv- |
Labour | (Time duration 5 Days) |
v- |
Development
Authority (SIDA/HRDA/MDDA) (Time duration 5 Days) |
vi- |
Revenue
Department. (Time duration 5 Days) |
Then DM/DIC Approved the In Principle Approval
for a Project. |
3-
Applying for State
Subsidy |
4-
Consent To Establish
(CTE) from Single windows. |
i-
|
Pollution NOC | (15 Days to 6 Month)
|
ii-
|
SIDA | (15 Days to 45 Days)
|
iii- |
Fire NOC | (15 Days to 30 Days) |
iv-
|
Labour Department
Permission for Boiler Setup .| (15 Days) |
v-
|
Water Connection
Only Required in Siidcul Haridwar.| (7 Days)
|
vi-
|
Electricity
Department | (15 days to 30 Days)
|
viii-
|
ETP/STP Connection | (7 Days)
|
5- |
Generate ID in IDS Portal for Subsidy.|
|
6- |
Soil Testing |
|
7- |
GST Registration |
|
8- Consent To Operate (CTO) |
i- |
Fire NOC | (15 Days to 30 Days)
|
|
ii-
|
Pollution NOC | (15 to 30 Days)
|
|
iii- |
SIDA -Occupancy Certificate | (30 Days To 6 month) |
|
iv-
|
Labour Department | (15 to 30 Days)
|
|
a- |
Factory Act license | |
|
b- |
Site Plan Approvals | |
|
c- |
Contact Labour Act | |
|
d- |
PF,ESIC Registration | |
9- |
CGWA | |
10- |
Complete IDS Subsidy Details. | |
- You will
ready to start Production/manufacturing .